Status

Engagement Status

Current progress, decision log, and open questions

Overall Progress

0%

Current Phase

Pre-engagement

Awaiting commercial sign-off

Phases Complete

0 / 7

Open Risks

10

5 high, 5 medium

Phase 0: Discovery and Detailed DesignPlanned

Weeks 1-2 | Owners: Atta, Saad

Phase 1: DR-Readiness FoundationsPlanned

Weeks 2-3 | Owners: Atta, Saad

Phase 2: Secondary Region BuildoutPlanned

Weeks 3-6 | Owners: Saad, Atta

Phase 3: Data Replication SetupPlanned

Weeks 5-9 | Owners: Saad, Atta

Phase 4: App Deployment ParityPlanned

Weeks 8-11 | Owners: Saad, Atta

Phase 5: Full Failover DrillPlanned

Weeks 11-13 | Owners: Atta, Saad, Ahmad Khan

Phase 6: Handover and AcceptancePlanned

Weeks 13-16 | Owners: Atta, Ahmad Khan